HARBOURS & COASTS
ASHDOD NORTH PORT EXTENSION - ISRAEL
Client: Israeli
Ports and Railways Authority (PRA)
Services: Planning,
final design and works supervision
Period: 1997-1999
Construction cost:
277,647,229
The project:
Preliminary and detail design of the port extension works.
The port of Ashdod is one of the few deep water ports built on
the open sea. Many engineering challenges were encountered
during its construction between 1961 and 1965. The original
port layout included two breakwaters for a total length of
over 3 km, a 300 m wide entrance channel and 3,5 km of quays
on a maximum water depth of 14 m. In 1994 the port handled
14.2 million tons of cargo, registering a 6% increase over the
1993 traffic and an increase in container traffic of over 10%.
The port also handled some 138,000 passengers.
Due to the increasingly heavy traffic demands and predictions
of future growth, massive extension works have been planned by
the PRA. The new project involves the planning, final design
and general supervision of the port extension works to be
carried out in two stages:
Stage A
includes the extension of the port to the north, with the
extension of the main breakwater and the creation of a modern
container terminal, a general cargo and dry bulk terminal, and
Ro-Ro ramps. In particular the following works are planned:
*
construction of 5 new quays on 16 m depths
*
extension of the main breakwater by over 1000 m on 20 m depths
*
construction of a temporary port with an 800m sea wall and 300
m quay for use by the contractors during construction
* dredging
of the new port basin for some 2.5 million cu. m.
* construction
of a service area of some 400,000 sq. m. with connections to
road, rail and utility networks
Stage B
includes the further extension of the port to the north, with
the construction of a new lee breakwater, expansion of the
container terminal and construction of a new coal terminal
(which could also be used for general and dry bulk cargo. The
works foreseen include:
*
construction of new lee breakwater approx.900 m long
*
construction of 4 new quays on 19 m depths
*
dredging of the new port basin for some 2 million m3
*
construction of a service area of some 200,000 sq. m. with
connections to road, rail and utility networks.
The design period is expected to last two years, with a
further 4 years for construction.
TECHNITAL is carrying out the project with the following
sub-contractors: Grabowsky & Poort and the Port of Rotterdam
(The Netherlands), and the Israeli firms Muller-Shnabel-Zachar
& Partners, and Leonardo Stadler,
Back to Harbours and Coasts

|